Setting up simple Release Procedure for Purchase Requisitions

Willem Hoek on Feb 11, 2006

Release Procedures (approval) can be used for Purchase Requisitions (PR), Purchase Orders (PO), RFQ’s, Outline Agreements and Service Entry Sheets. The principle is exactly the same for all. If you can master one, you will know them all.

Lets set up release procedures for PR for the following example:

Our company have got 2 plants: Plant 3100 (London) and plant 3600 (New York).

image

Key terminology:

Here is a summary of the steps to follow to set up our example:

Detail steps of setting it up

Create Characteristics & link to communication structure (CEBAN for PR)

Here we define which fields are used to determine the strategy that will kick in. In our case we used ‘Plant’ and ‘Item value’. Not all fields in the PR can be used. For a full list of fields that can be used to determine the release startegy, see tcode se12 table CEBAN.

image

image
image

So the two fields that will be used is:

Field CEBAN-WERKS for Plant
Field CEBAN-GSWRT for Item Value

We need to create a characteristic for every field. Use transaction ct04 Any characteristic name can be used. Keep something descriptive to avoid confusion.

For Item Value – lets create characteristic Z_GSWRT

image

First go to Additional Data tab and enter the table/field (and Enter)

image

Enter currency to be used in the Basic data tab. Also select multiple values _and _Intervals allowed

The Intervals allowed will allow us to assign a range of values, example: If PR value is 0 - 1000 USD …..

image

Save the characteristic

For Plant – characteristic Z_WERKS
Again, the table/field name in Additional Data to enter table/field

image

Again set multiple values and save the characteristic
The multiple values is to assign more than one plant to strategy, example: If PR for plant 3100 and plant 3600 is …

Create Class & link to characteristic

Create a class (simply to group the characteristics). Again any name can be used. Tcode CL01 – Create Class. The Class Type must be 032.

image

Configure Release Procedures

Above actions was all master data. We now need to do some configuration. Menu: IMG > Materials Management > Purchasing > Purchase Requisition > Release Procedure > Procedure with classification > Set up procedure – (tcode OMGQ in older SAP versions)

image

Create Release Groups & link to class

We have two groups to create AA and AB. We need to indicate the class we are working with, in out case Z_PR.

image

Create Release Codes

Create all the release code / group combinations. This is all the dots in diagram above. So we have 4.

image

Later on, authorisation profiles will be linked to these code / group combinations.

Release Indicator

First we create the different statusses that the PR can be in throughout it lifecycle. Later on (below), we will be linking using these statusses. Here is the standard SAP indicators, wou probably wouldn’t need to add any.

image

We will be using two of these – X (Block) and 2 (Released)

image

image

Under the Details section, you can indicate which documents can be created from this PR. For Indicator 2, one can create PO’s and RFQ’s.

With _Field Selection _you can define which fields can be changed. This is the same indicator that gets used with document type configuration to make some fields read only, mandatory, hidden.

Set up strategies - Strategy & Codes

Every line in our diagram above is a strategy. So We have three Lets call them:
Group AA / Startegy S1 – Code L1 (for plant 0001)
Group AA / Startegy S2 – Code L1 & L2 (for plant 0001)
Group AA / Startegy S2 – Code L1 & L2 (for plant 0002)

image

Here are the settings for AA / S2

image

Set up strategies - Prerequisites

For every strategy, we need to define a release prerequisites. This indicate if one code need to take place before the other. In this case, level 2 (L2) can only take place if level 1 (L1) has been released.

image

Set up strategies - Status

This is also done for every strategy. The screen is dependant on what groups were linked to the strategy as well as prerequisites that was set up. In this example:

Out of interest, the reason why there is not a L2 only option is because of the setting in the prerequisites.

image

Set up strategies - Values for strategies

The values linked to strategies are master data (not configuration) and can be set in two places. Either within the configuration itself – selecting the classification button

image

image

Or, in classification, example CL24N

image

image

Both methods work, the advantage of CL24N is that all the strategies can be viewed easier.

Set overall / item for doc type (PR only)

For Puchase Requisitions, there is an option to release either on item level or on document level. For PO / RFQ / Contracts, one can only release on header level. Back to the PR, it is highly recommended to use item release. This can be done in two places.

Firstly where the groups were created

image

On the document type configuration for PR
Config menu: Materials Management > Purchasing > PR > Define document types

image

Create and allocate authorisation profiles

In our example we will have three people releasing, so three profiles will need to be created. Authorisation profiles can be created using tcode PFCG.

Usage of PFCG are not being discussed here, but see below for relevant screen where the profile was created.

image

————— USING RELEASE PROCEDURES —————

Create a Purchase Requisition

Lets create a PR, and see if the release procedure kicks in. In our case we will create it for plant 3600 and any value. So we will expect Strategy AB / S2 to kick in.

Create PR – me51n

image

If no ‘Release strategy’ tab, then it didn’t work. In this case all is fine. The user can see the Release Group (AB), Strategy (S2) and release indicator (X).

(SAVE)

Release a Purchase Requisition

Releasing can be done per PR or collective. Lets’ use the collective release. SAP Menu: Logistics > Material Management > Purchasing > Purchasing Requisition > Release > Collective ReleaseME55

image

Select all the items to be released and then hit Save. You will see the status of the item change to the next Release Indicator.

image

This is the absolute basics of setting up Release Procedures for Purchase Requisitions. For more posts on Release Procedures, see index of posts.